Launch of Bangkok’s two new electric rail strains delayed

Due to development material problems, the debut of Bangkok’s two new electrical rail lines, the Yellow and Pink strains, scheduled for later this yr, is prone to be pushed back till no later than next yr, based on Bangkok Mass Transit System.
Fail-proof will give contractors additional time to deal with obstacles and hurdles in importing building supplies from other international locations, which the Covid-19 outbreak over the past two years.
The organisation will ask the Thai Mass Rapid Transit Authority to prolong the timeframe for launching the 2 traces by another 677 days. Service on the expanded traces will begin no later than 2023, in the worst-case scenario.
The Pink Line, which is around 34.5 kilometres long, was round 85% finished as of last month, while the 30.4-kilometre Yellow Line was 90% accomplished. BTSC will aim to hurry the completion so they are available for use by the end of 2022. Be the first were meant to be in service final yr, but as a result of virus outbreak, they had been pushed back..

Leave a Comment